How to Record Extra Work

The best record is the one made on site. This is a short routine you can hand to a supervisor or foreman.

On site, straight away

Before anyone starts the work:

  • Photograph the area as it currently stands
  • Write down what has been asked for in one or two plain sentences
  • Record who asked, their company and the time
  • Note the exact location on site

Same day, back in the office

Price the instruction into a variation with labour, materials, plant, subcontractors, markup and VAT, and send it for approval. Speed matters — approval is much easier to obtain before the work is done.

On completion

Photograph the finished work from the same angle as the before photo and add a short completion note. That pairing is the strongest evidence you can hold.